British Rail Class 777
The British Rail Class 777 Metro[6] is a class of electric multiple-unit passenger trains currently under construction by Swiss rolling stock manufacturer Stadler Rail, to be used on the Merseyrail network in the Liverpool City Region and the Wirral Peninsula.[7] Ordered in 2016, construction of the units began in 2018.[8] As of August 2021, trains are due to enter service in 2022, replacing the oldest fleet of trains in the UK.[9]
| British Rail Class 777 Metro | |
|---|---|
![]() 777010 standing at the platform at Hooton | |
| In service | 2022 (planned) |
| Manufacturer | Stadler Rail |
| Built at | Altenrhein, Switzerland Siedlce, Poland[1] |
| Family name | Metro |
| Replaced | [2] |
| Constructed | 2018–2021 |
| Number under construction | 53 units to be built An option for a further 59 extra units is available[3] |
| Formation | 4 carriages per train |
| Fleet numbers | 777001–777053 |
| Capacity | 182 seats[2] |
| Operator(s) | Merseyrail |
| Depot(s) | |
| Line(s) served | |
| Specifications | |
| Train length | 64.98 m (213 ft 2 in) |
| Car length | TBC (DTSO) TBC (TSO) |
| Width | 2.82 m (9 ft 3 in) |
| Height | 3.82 m (12 ft 6 in) [4] |
| Floor height | 0.96 m (3 ft 2 in) |
| Doors | 2 × twin sliding doors (DTSO) 4 × twin sliding doors (TSO) |
| Maximum speed | 75 mph (121 km/h) |
| Weight | 99 t (97 long tons) |
| Traction system | IGBT–VVVF |
| Power output | 2.1 MW (2,800 hp)[5] |
| Acceleration | 1.1 m/s2 (2.5 mph/s) [4] |
| Electric system(s) | 750 V DC third rail |
| Current collection method | Contact shoe |
| UIC classification | 2'(Bo)'(Bo)'(Bo)'2'[4] |
| Safety system(s) | AWS TPWS |
| Coupling system | Dellner |
| Multiple working | Within class |
| Track gauge | 4 ft 8+1⁄2 in (1,435 mm) standard gauge |
History
Background
The replacement of the Class 507 and Class 508 fleet that has been in use on the Merseyrail commuter rail network since the late 1970s, had been proposed by Merseytravel as early as 2011.[10] While the Class 507 and 508 weren't the oldest electric multiple-units in use in Great Britain, Merseytravel had the oldest average fleet.[9]
In 2014, Liverpool City Region set out a 30 year rail vision, outlining investments that would and could be made to improve rail transport in the region. This included replacement of both the Class 507 and 508 trains with a new high capacity, dual voltage train fleet.[11] In 2015, Merseytravel gained approval to go out to tender to replace the train fleet.[12] In January 2016, Merseytravel announced that a total of five rolling-stock manufacturers had been shortlisted to build the new fleet – Bombardier, Siemens, CAF, Stadler Rail and a Mitsui/Alstom/East Japan Railway Company consortium.[13]
Contract award
On 16 December 2016, Merseytravel announced Stadler Rail would manufacture a new fleet of 52 dual-voltage-capable articulated four-car units as part of a £460 million fleet replacement project.[3][14][15] Merseytravel has an option for a further 60 units.[3] Delivery of the Class 777 fleet was scheduled to start in mid-2019, and its entry into service was set for the following year.[14] The new trains would increase capacity by 60%, as well as cutting journey times due to faster acceleration.
The purchase was financed by Liverpool City Region itself, rather than an external agency such as a bank or rolling stock leasing company.[10] The Class 777 trainsets will therefore be owned by the regional public transport operator Merseytravel and leased to the franchise operator Merseyrail; this made Merseytravel the only public-sector mainline rolling-stock owner in the United Kingdom.[10] This is unlike the preceding fleet, owned by the private leasing agent Angel Trains.[10]
Merseytravel elected to have the new fleet's maintenance requirements addressed via a contract with Stadler; this arrangement included the modernisation of two existing traction maintenance depots (TMDs), at Kirkdale and Birkenhead North. For training purposes, a driver cab simulator has been installed in Kirkdale TMD.[10]
When the plan for an extension of the Kirkby line to Headbolt Lane was announced to the public, it was also revealed that the original order of 52 units had been increased to 53, in order that Stadler could supply sufficient units to operate the Kirkby line service once extended, as four diagrams will be required rather than three as at present.
Infrastructure modifications
To accommodate the new Class 777 trainsets, extensive infrastructure changes were necessitated.[10] These adaptations were performed under a rolling programme between October 2018 and May 2019; changes included adjustments to 97 platforms at 56 stations across the Merseyrail network, along with track realignments and other refinements, primarily for the purpose of improving passenger accessibility. Another cause for the alterations was the increased length of the new trainsets, which was addressed via a mixture of platform lengthening and signal repositioning where required. The programme was structured as to minimise disruption to Merseyrail's scheduled services wherever possible.[10] A new trackside Wi-Fi network, provided by Panasonic, was installed to provide continuous real-time connectivity between all trains and the Sandhills control centre, along with free internet access for passengers. New bulk power supplies were installed, along with eight new substations and miscellaneous cable upgrades, to provide greater quantities of electricity.[10]
Unlike the preceding trains, the Class 777 was designed to be operated without guards; however, the announced proposal to redeploy guards into other customer service roles within Merseyrail was subject to considerable criticism.[16] Accordingly, while the fleet was initially to be launched under driver-only operations, in September 2018 it was announced that there would be a second member of staff on board, ending a two-year dispute between the National Union of Rail, Maritime and Transport Workers (RMT) and Merseyrail.[17]
Testing and delivery
.jpg.webp)


During early October 2018 the bodyshells for the first unit were completed.[8] This unit subsequently underwent pre-delivery dynamic testing in both Switzerland and Germany during late 2019.[18][19] The first trainset, 777003, was delivered to Kirkdale TMD on 16 January 2020.[20][21] On 16 March 2020, the unit commenced test runs on the Kirkby branch of the Northern Line.[22] By October 2020, ten units had been delivered to Kirkdale TMD.[23]
In 2018, it was announced that a train configured as a battery electric multiple unit was to be tested on sections of unelectrified track.[1][24] Following the trial, it was announced in July 2021 that the units tested had been able to travel up to 20 miles without the need for recharging. The Liverpool City Region Combined Authority announced that the battery-powered trains will run to the new Headbolt Lane station at Kirkby which is due to open in 2023.[25]
In July 2021, full daytime testing of the units was underway.[26] In August 2021, the Office of Rail and Road authorised the introduction of these units into passenger operation.[9] As of December 2021, the date for passenger service has not been announced.
Design
As part of the Stadler Metro train family, the units are built on the same platform as the BVG Class IK stock used on the Berlin U-Bahn and future units being developed for the Minsk Metro and Glasgow Subway.[6] The trainsets are configured for high-capacity, delivering a 50 per cent increase in per-carriage capacity than the preceding fleets.[10] It has a higher rate of acceleration, yet uses 20 per cent less energy than the old rolling stock, due to increased system efficiency and a reduced weight, being roughly 5.5 tonnes lighter. The introduction of the Class 777 is reportedly set to achieve a 10 per cent reduction in journey time over older stock, attributed to its greater rate of acceleration.[10] There is also an emphasis on shared data; each train will actively monitor the number of passengers on board and relay this to Merseyrail's Sandhills control centre, allowing for more informed and responsive management of the network.[10]
Each Class 777 trainset has two longer driving cars positioned at each end, with one set of twin doors on either side, whilst the two middle trailer carriages have two sets of doors. For accessibility purposes, all doorways have been outfitted with sliding steps that move into position when the train is stopped at a platform, enabling passengers using wheelchairs to board and disembark without relying upon a separately deployed ramp.[27] The carriages will feature an open gangway design, the first class of train on the Merseyrail network to feature this design.[10] The passenger facilities are much improved over legacy stock, each carriage being fitted with modern amenities such as electrical and USB sockets, as well as bike racks. Like the previous Class 507 and 508 fleets, the Class 777s will not be fitted with toilets.[10] As part of the bespoke design, an LED letter 'M' has been sandwiched between the headlight clusters, illuminating yellow on the front of the train, and red on the rear.[28]
The train is dual voltage, allowing it to be powered via the third rail, which is present across Merseyrail's existing network - as well as running under 25 kV AC overhead wires if required in future.[1][10] Due to safety concerns, any future extensions will be electrified via overhead wires instead of installing a third rail power supply. The Class 777 is also capable of being configured as a battery electric multiple unit (BEMU), enabling it to operate on a mixture of electrified and unelectrified track.[25] The Class 777 will be fitted with compact battery sets, which allow for brief periods independent movement; this is intended to be used around workshop and maintenance facilities, rather than during any scheduled service.[29]
Fleet details
| Class | Operator | No. Built | Year Built | Cars per Set | Unit nos. |
|---|---|---|---|---|---|
| Class 777 | Merseyrail | 52 + 1 | 2018–2021 | 4 | 777001–777053 |
| 60[lower-alpha 1] | TBC | 777054–777113 | |||
- An option for another 60 units is available.[3]
References
- "Battery trial planned for new EMU fleet". railwaygazette.com. 25 May 2018.
- "ORR authorises Merseyrail and SWR fleets". Rail. No. 938. 25 August 2021. p. 12.
- "Stadler signs contract to build and maintain 52 metro trains for Liverpool City Region" (PDF) (Press release). Stadler Rail. 16 February 2017. Retrieved 13 May 2019.
- "Metro Merseyrail EMU" (PDF). Stadler Rail. n.d. Retrieved 16 April 2017.
- "Class 777 Vehicle". MerseyRail. Retrieved 11 September 2021.
- "Products". Stadler Rail. Retrieved 14 January 2019.
- Barrow, Keith (16 December 2016). "Stadler to supply new Merseyrail trains". International Railway Journal.
- Clinnick, Richard (1 October 2018). "First Merseyrail Class 777 bodyshells complete". Rail. Peterborough.
- "Two new British EMUs receive authorisation for passenger use". International Railway Journal. 6 August 2021. Retrieved 21 August 2021.
- Darlington, Paul (29 June 2020). "New MerseyRail 'connected' trains". Rail Engineer.
- "Liverpool sets out 30-year rail vision". International Railway Journal. 28 August 2014. Retrieved 21 August 2021.
- "Merseytravel seeks £400m investment". International Railway Journal. 3 September 2015. Retrieved 21 August 2021.
- "Merseytravel names five international bidders in new fleet and depot shortlist". Rail Technology Magazine. Manchester. 12 January 2016. Retrieved 16 December 2016.
- "New Merseyrail trains by 2020 after City Region leaders give green light" (Press release). Merseytravel. 16 December 2016. Archived from the original on 16 October 2019. Retrieved 14 January 2019.
- "Stadler to supply 52 EMUs for Liverpool". International Railway Journal. 17 February 2017. Retrieved 21 August 2021.
- Houghton, Alistair (16 December 2016). "Merseytravel reveals new £460m train plans - with no train guards". Liverpool Echo.
- "Liverpool City Region, Merseyrail, RMT end long-running guard dispute". www.railtechnologymagazine.com. 6 September 2018. Retrieved 17 September 2018.
- Devereux, Nigel (4 November 2019). "Factory commissioning of Merseyrail Class 777 begins". therailwayhub.co.uk.
- Clinnick, Richard (27 August 2019). "Progress on new train fleets continues". Rail. Peterborough.
- "The first new train is in the UK and on the way to the city region!" (Press release). Merseytravel. 15 January 2020.
- Holden, Alan (28 January 2020). "Metro Mayor Welcomes New Class 777 Train to Merseyrail". railadvent.co.uk.
- Tyrrell, Nick (16 March 2020). "New Merseyrail trains testing in Liverpool with key new feature". Liverpool Echo.
- "Merseyrail Class 777 Deliveries". Rail Record. 20 May 2020. Retrieved 26 July 2020.
- "Long Term Rail Strategy – update" (PDF). Liverpool City Region Combined Authority. 24 October 2017. Archived from the original (PDF) on 7 November 2017. Retrieved 16 March 2018.
- "Battery breakthrough will see Merseyrail network extended". Liverpool Business News. 21 July 2021.
- "Daytime testing begins for new Merseyrail trains". Liverpool Business News. 1 July 2021. Retrieved 21 August 2021.
- "Merseyrail EMU" (PDF). Stadler Rail. Stadler Rail. Archived from the original (PDF) on 3 August 2018. Retrieved 3 January 2018.
- Houghton, Alistair (15 August 2018). "First look inside futuristic new Merseyrail trains". Liverpool Echo. Retrieved 13 March 2019.
- "Stadler signs contract to build and maintain 52 metro trains for Liverpool City Region". Stadler. Retrieved 14 January 2019.
External links
| Wikimedia Commons has media related to British Rail Class 777. |
- List of Merseyrail Class 777 units and the dates they were delivered to Merseyrail (rail-record.co.uk).