Timeline of the James Webb Space Telescope
The James Webb Space Telescope is an international 21st-century space observatory scheduled to be launched on December 22, 2021.[1] It is intended to be the premier observatory of the 2020s, combining the largest mirror yet on a near-infrared space telescope with a suite of technologically advanced instruments from around the world.[2]

.jpg.webp)


.jpg.webp)
The telescope is designed to last at least five and a half years (six months calibration plus five years science operations), but with a goal of ten years.[3] The limiting factor is expected to be fuel to maintain its halo orbit, of which there is enough for at least ten years.[3]
JWST is expected to cost at least $8.8 billion, including design, construction, and five years of operations (does not include extended mission funding) or International contributions.[4][5]
Timeline of selected events
- 1996: Next Generation Space Telescope initiated.[6]
- 2000: NEXUS cancelled (JWST technology demo).[7][8]
- September 2002: NGST named James Webb Space Telescope.[6][2]
- September 11, 2003: $824.8 million prime contract for JWST awarded to TRW.[9]
- January 2007: 9/10 technology development items pass non-advocate review.[10]
- April 2010: technical part of Mission Critical Design Review (MCDR) passes.[11]
- July 2011: James Webb project threatened with cancellation.[12][13][14][15]
- November 2011: JWST survives cancellation attempt.[16]
- 2012: MIRI instrument hand-off.[17]
- March 2013: FGS/NIRISS installed in ISIM.[18]
- July 4, 2013: MIRI installed in ISIM.[19]
- March 2014: NIRCam installed in ISIM[20]
- March 24–25, 2014: NIRSpec integrated into ISIM.[21]
- June 2014: first combined test of all four instruments including cryogenic testing in the Goddard Space Environment Simulator.[22]
- 2014: peak U.S. funding hit with $650 million this year.[4]
- February 2015: hexagonal segments of the primary mirror completed.[23]
- December 2015: contract for JWST's launcher signed with a launch date of October 2018.[24]
- March 2016: cryogenic testing of instruments and mirrors completed.[25]
- March 3, 2016: secondary mirror installed on OTE.[26]
- March 2016: Aft Optics Subsystem installed on OTE.[27]
- November 2016: JWST construction completed (still needed testing, etc.)[28]
- January 2017: JWST is fine after experiencing an anomaly during vibration testing in Dec 2016.[29]
- March 27, 2018: JWST launch delayed to at least May 2020 as issues with the spacecraft element require further testing.[30]
- June 27, 2018: JWST launch postponed to March 30, 2021 based on recommendations by an Independent Review Board.[31]
- July 16, 2020: JWST launch postponed to October 31, 2021 due to impacts from the coronavirus (COVID-19) pandemic, as well as technical challenges.[32]
- June 1, 2021: JWST launch postponed to no earlier than November 2021 due to concerns regarding the readiness of the Ariane 5 launch vehicle and launch site.[33]
- September 8, 2021: JWST launch postponed to December 18, 2021.[34]
- November 22, 2021: JWST launch delayed to no earlier than December 22, 2021, to allow additional testing after experiencing vibrations due to an unplanned clamp release.[35]
Pre-launch plans
- 2016: OTE tests complete.
- 2017: OTIS tests complete.
- 2017: Spacecraft (including sunshield) tests complete.
- 2018: Observatory I&T complete.
- October 2018: planned launch date as of 2016.[2]
- Early 2019: planned launch date as of October 2017.[36]
- May 2020 or later: planned launch date as of March 2018.[37]
- March 30, 2021: planned launch date as of June 2018.[31]
- October 31, 2021: planned launch date as of July 2020.[32]
- November 2021 or later: planned launch date as of June 2021.[33]
- December 22, 2021: planned launch date as of November 2021.[34]
- December 24, 2021: planned launch date after delay due to communication issues between the observatory and the Launch Vehicle.
After-launch plans
- After launch it is unfolded in the following planned order.[38]
- 1) spacecraft appendages (solar arrays, high gain antenna)
- 2) sunshield
- 3) extend tower
- 4) secondary mirror
- 5) primary mirror
- For 30 days after launch it takes a million mile trip to L2 halo orbit[39]
- For six months JWST prepares for full-time science operation. This includes letting everything cool down, calibrating the mirrors and instruments, etc.[40]
- Five year science mission starts after six months (planned)[40] (so five and a half years minimum planned)
- 10 years of operation goal, and enough fuel to maintain halo orbit for at least ten years is included.[3]
After-launch deployment

Nearly a month after launch, a trajectory correction will be initiated to place the James Webb Space Telescope into a halo orbit at L2.[42]
References
- "NASA Provides Update on Webb Telescope Launch – James Webb Space Telescope". blogs.nasa.gov. Retrieved 2021-11-23.
- "The James Webb Space Telescope". Explore James Webb Space Telescope. NASA. Archived from the original on 1 June 2006. Retrieved 3 December 2016.
- "The James Webb Space Telescope". www.asu.edu.
- "Manufacturing Issues Plague James Webb Space Telescope". SpaceNews. November 15, 2014.
- Witze, Alexandra (2018-03-27). "NASA reveals major delay for $8-billion Hubble successor". Bibcode:2018Natur.556...11W. doi:10.1038/d41586-018-03863-5. Retrieved 2018-03-27.
- "About James Webb". NASA. Retrieved 15 March 2013.
- "Nexus Space Telescope". MIT.
- "Multidisciplinary Analysis of the NEXUS Precursor Space Telescope" (PDF).
- "TRW Selected as JWST Prime Contractor". STCI. 11 September 2003. Archived from the original on 5 August 2012. Retrieved 13 January 2012.
- "JWST Passes NTAR". STScI. Archived from the original on 5 August 2012. Retrieved 5 July 2008.
- "NASA's Webb Telescope Passes Key Mission Design Review Milestone". NASA. Retrieved 2 May 2010.
- McKie, Robin (9 July 2011). "Nasa fights to save the James Webb space telescope from the axe". The Guardian. London.
- "Appropriations Committee Releases the Fiscal Year 2012 Commerce, Justice, Science Appropriations". US House of representatives Committee on Appropriations. 6 July 2011.
- "US lawmakers vote to kill Hubble successor". SpaceDaily. 7 July 2011.
- "Proposed NASA Budget Bill Would Cancel Major Space Telescope". Space.com. 6 July 2011.
- "NASA budget plan saves telescope, cuts space taxis". Reuters. 16 November 2011.
- "Europe delivers first JWST instrument". sci.esa.int. Retrieved 2017-11-12.
- GMS, NASA's (March 11, 2013). "GMS: FGS/NIRISS Installation into the ISIM Structure". svs.gsfc.nasa.gov.
- "ESA Science & Technology - MIRI installed in ISIM". sci.esa.int.
- "Lockheed Martin Readies One of the Most Sensitive IR Instruments Ever Made for NASA Telescope". Media - Lockheed Martin.
- "NIRSpec is integrated into ISIM". sci.esa.int. Retrieved 2017-11-12.
- "ESA Science & Technology - #07: Summer 2014 - first combined test of all four instruments". sci.esa.int.
- "NASA's James Webb Space Telescope Primary Mirror Fully Assembled". NASA.gov. 3 Feb 2016. Retrieved 4 Feb 2016.
- "ESA Science & Technology - ESA confirms James Webb telescope Ariane launch". sci.esa.int.
- Jenner, Lynn (2016-03-21). "NASA Marks Major Milestones for the James Webb Space Telescope". NASA. Retrieved 2017-11-12.
- Jenner, Lynn (2016-03-07). "NASA's James Webb Space Telescope Secondary Mirror Installed". NASA. Retrieved 2017-11-12.
- "GMS: JWST Aft-Optics System (AOS) Installed at GSFC". Retrieved 5 December 2016.
- "Nasa begins testing enormous space telescope made of gold mirrors". the Guardian. November 4, 2016.
- "No damage to JWST after vibration test anomaly". SpaceNews.com. 2016-12-23. Retrieved 2017-11-12.
- "James Webb Space Telescope, NASA's next Hubble, delayed again". CNET. 2018-03-27. Retrieved 2018-03-27.
- "Jim Bridenstine on Twitter". Twitter. Retrieved 2018-06-28.
- "NASA Announces New James Webb Space Telescope Target Launch Date". nasa.gov. Retrieved 2020-07-20.
- Berger, Eric (1 June 2021). "Webb telescope launch date slips again". Ars Technica. Retrieved 2 June 2021.
- "About Webb Launch - NASA". ESA. Retrieved 8 September 2021.
- "NASA Provides Update on Webb Telescope Launch – James Webb Space Telescope". blogs.nasa.gov. Retrieved 2021-11-23.
- "JWST launch slips to early 2019 – Spaceflight Now". spaceflightnow.com. Retrieved 2017-11-12.
- "NASA Delays Launch of James Webb Space Telescope Until 2020". Space.com. Retrieved 2018-03-27.
- "Deployment". wayback.archive-it.org.
- "The Launch - Webb/NASA". jwst.nasa.gov.
- "Orbit - Webb/NASA". jwst.nasa.gov.
- "FAQ Full General Public Webb Telescope/NASA". jwst.nasa.gov.
- "James Webb Space Telescope – The First 30 Days After Launch". News Ledge. 2017-03-03. Retrieved 2017-05-30.